|
MISSION STATUS
(updated Feb 9, 2002)
Feb 9, 2002, 10:30AM PST:
All systems are working as planned. No problems. From
now on, we will reduce the number of announcements in
this list. For a detailed description of the passes please
check the HESSI Major Events
.
Feb 6, 2002, 5:15PM PST: Soon the solid state recorder will be turned on. Downlink now
is 1Mbit per second. The cryocooler is operating at 85% of the
power. The particle detector is turned on
and working well.
Feb 5, 2002, 10:25 PM PST:
The cryocooler was turned on for the first time
Feb 5, 2002, 5:15 PM PST:
Everything is still hunky dory. The 2nd
pass went fine. We are within 5 degrees of the sun. Command uplink and
downlink is strong. Next big
events: crycooler turn-on (at about 8PM PST) and start spinning up.
Look at the HESSI Major Events
page for details about the passes.
Feb 5, 2002, 4:15 PM PST:
Press articles:
Feb 5, 2002, 4:07 PM PST:
From Brian Dennis, HESSI Mission Scientist:
I'm pleased to report that HESSI telemetry was picked up at Berkeley and
at
Wallops on the first orbit and that everything looks nominal. The solar
panels have deployed and the spacecraft is pointing close to the solar
direction. The orbit is very close to the nominal that
Peter Harvey gave in his
last email (see below) and the ground stations had no trouble picking up the
spacecraft.
Feb 5, 2002, 3:50 PM PST:
The sun is aquired within 15
degrees. Solar panels are deployed. Everything is nominal. Next pass
at 4:11 PST.
HESSI LAUNCH SUCCESSFUL.
From Peter Harvey, Project Manager:
HESSI was successfully launched today 4:08 PM EST. Based
upon launch vehicle data, the orbit is approximately
586.85 x 600.24 km at 38.023 degrees inclination.
The speceraft telemetry was good all the way through
launch with no anomalies.
Feb 4, 2002:
Over the weekend, tests of the launch vehicle and spacecraft
were successful. We continued charging the battery in preparation
for launch.
Today, we completed the Launch Readiness Review with all parties
giving the 'GO' for launch. Weather is also cooperating.
|
|
|
|
If all goes as planned, solar
images
will soon be returned by the HESSI space craft. SOHO image, courtesy of the SOHO project team.
|
MAJOR HESSI EVENTS DURING 2001
|
December 2001:
- OSC replaces rocket 1st stage skirt, motors and fins.
- New assembly passes vehicle verification tests.
- Final test of science detectors. All good.
- Structured warm up.
- Authorization to proceed at KSC meeting (LVRR).
- Spacecraft mated with rocket
November 2001:
- OSC verifies and replaces Fin Actuator System and Thrust
Vector Controller.
- OSC makes rocket software modifications (trajectory control)
as a result of X43 failure and wind tunnel data.
- OSC submits description of software changes to KSC.
- Interface Verification and Flight Sim 3 testing completed.
October 2001:
- OSC removes fin control electronics to check for contamination.
- OSC announces plan for additional wind tunnel testing.
- OSC carries out additional wind tunnel testing.
September 2001:
- Spacecraft and detector tests performed.
- Begin structured warmup using cryocooler.
- Return to LN2 cooling.
- Failure of OSC Taurus launch. OSC reviews causes and whether
there are implications for Pegasus.
- Successful Athena launch from Alaska. KSC staff returns
to complete review of questions related to X-43.
August 2001:
- Maintenance cooling with LN2.
- Regular monitoring of temperatures and pressure.
July 2001:
- Hessi demated from Pegasus rocket.
- Structured cooldown using cryocooler.
- High voltage turned on and detectors checked out. All good.
- Spacecraft turned vertical, cryocooler turned off and maintenance
cooling with LN2.
June
2001:
- Rocket with Hessi on L-1011 flies to KSC.
- Post flight testing of rocket and satellite.
- Continued testing of Berkeley Ground Station.
- Setup and checkout of Santiago Ground Station.
- X-43A test flight fails, causing delay of Hessi launch.
- Hessi returns to VAFB to await launch authorization.
May 2001 (VAFB):
- Pegasus rocket successfully completes Qualification testing.
- Performed structured warmup of Hessi detectors.
- HESSI mated with Pegasus rocket.
- Fairings installed.
- Pegasus with Hessi moved to transport trailer.
April 2001 (VAFB):
- Continuing Attitude Control System simulations
and tests.
- Continuing to practice flight operation
procedures.
- Moved spacecraft to Bldg 1555 at VAFB.
- Identified and corrected minor anomaly
with transponder.
March 2001 (VAFB):
- Completed setup of Hot Bench at UCB
and performed Attitude Control System simulations and tests.
- Moved spacecraft and GSE to Building
1610 on higher ground at VAFB to avoid power outages and flooding.
- Completed 4 Day No Command test.
- Practising flight operations procedures.
February 2001 (VAFB):
- Attached solar panels and performed 1st
Motion Test.
- Repeated spacecraft and instrument functional
tests.
- Reviewed and tested flight operations procedures.
- Presented mission status and readiness to PreShipment and
Red Team Reviews.
January 2001 (JPL and VAFB):
- Spacecraft returns to thermal vacuum for testing of cryocooler
performance at 50W and amplifier trims. Thermal Vacuum successfully
concluded on January 8.
- Mass Properties Measurements and Spin Balance performed
on January 9 and 10.
- Spacecraft transported to VAFB on January 12.
- Setup and Safe-to-Mate testing performed January 13-14.
- Spacecraft functionals and calibrations successfully performed
on Jan 15-17.
|
MAJOR HESSI EVENTS DURING 2000
December:
- Solar array deployment in thermal vacuum successfully tested.
- Endurance thermal-vacuum testing including hot and cold
dwells and extended thermal balance testing.
- Learned that spectrometer is colder than expected at planned
cryocooler power level. Good news: we can operate with less
power.
- Observed hf noise on two detectors.
- Made amplifier trims to correct noise problem.
November:
- Spacecraft transported to JPL on November 1-2.
- Preliminary setup and testing performed.
- Solar Arrays attached and deployment tested.
- Vibration testing of X , Y and Z axes successfully completed.
- Separation/shock testing successfully completed.
October:
- Flight battery reconditioned and installed.
- Spacecraft fully functional and running.
- Red Team and Pre-Environmental Reviews.
September:
- Ran and passed the following spacecraft functional tests:
command and data handling, inertia adjustment device, thermal,
launch vehicle interface, electrical power system.
August:
- The Spacecraft Electronics Module, Solid
State Recorder, Sun Sensors and Magnetometer have been returned
from subcontractors and re-installed on the spacecraft. All
units checked out OK.
- Requalified Transponder and RF Switch
received and installed on the spacecraft.
- Safe-to-Mate functional tests run for
all components.
July:
- Solid State Recorder, Transponder, RF
Switch, Sun Sensors and Magnetometer all removed from the
spacecraft and delivered to the
subcontractors for retesting and qualification.
- The Spacecraft Electronics Module completed
testing at Spectrum Astro by the end of the month and checked
out OK.
June:
- New deck completed and installed.
- Refurbished bus structure completed and
aligned.
- New imager support ring completed and
installed.
- Implementing several plans running in
parallel to provide new spectrometer cryocooler.
- New solar array substrates completed
at COI.
- Requests for Action received from May
review team. Spacecraft Electronics Module shipped back
to Spectrum Astro.
- GPMC authorizes new integration, test
and launch plan on condition that cryocooler issue is resolved
by September. New launch date set for March 2001.
May:
- Spacecraft minus imager and spectrometer
taken to Bell Labs for thermal test. From May 2 to May
5 spacecraft undergoes 6 cycles between +45 and -20C.
Spacecraft passes all functional tests except for firing of
frangibolts. Problem is found to be a broken wire
which is fixed. All other wiring is scrutinized and
plans prepared for high pot and other testing.
- Designed stronger imager support ring.
- Decided to repair broken solar panels
and also contract new panels to have two options and choose
the best in future.
- Honeycomb deck found to be slightly warped.
Began fabrication of new deck.
- Spectrometer cryocooler found to have
deteriorating performance since mishap.
- Spectrometer cryocooler flight spare
starts also exhibiting problems during burn-in tests.
- Termination/Recovery Review held at UCB
on May 15 and 16.
- HESSI Test Mishap Investigation Board
issues their report on May 18.
- After the thermal test and fix of frangibolt
wiring, spacecraft is powered up and running most days.
- Flight operations team continues preparations,
including simulations of Launch and Early Orbit plus regular
passes.
April:
- Spacecraft carefully inspected and found
to be in good shape with the following exceptions: two
damaged solar arrays, broken imager support ring,
one strained cable.
- Review meeting between GSFC and UCB held
on April 4. Recommendation is to do more inspection
plus a thermal test.
- Imager (which rests on the broken imager
support ring) shipped to PSI so they can fully test and recalibrate.
- Spectrometer removed and tested for leaks.
None found.
March:
- Solar arrays integrated and thermal blankets
installed.
- Spacecraft shipped to JPL.
- Pass EMC testing.
- Pass random vibration testing.
- Spacecraft over-vibrated in sine-burst
test (20 G's applied instead of 2 G's for 200 milliseconds).
- Review team gathered to investigate the
over-test.
- Spacecraft shipped back to UCB for inspection
and evaluation.
January/February:
- Spacecraft Bus delivered to UC Berkeley.
- All instruments successfully integrated
and tested at UCB's Spacecraft Integration Facility.
- Pass Environmental Reviews.
- Successful end-to-end testing of telemetry
and commands between spacecraft and ground system via the
11 meter antenna.
|
|
|